Minutes of the 118th Regularly
Scheduled Meeting
10:00 a.m., July 10, 2008
Call to order:
The 118th regularly scheduled
meeting of the Port Ludlow Drainage District (PLDD) was called to order by
Chairman, Commissioner Leland Amundson at 10:02 a.m.
PLDD Commissioners present
were Leland Amundson, Walter Cairns and James Laker.
The minutes of the
regularly scheduled May 8 and 12 June, 2008 meetings were approved as submitted.
Expenses:
·
The PLDD Commissioners discussed
and approved Drainage District expenses that accrued from 12 June 2008 to 9 July
2008 for the total amount of $5,871.20.
A breakdown of this total is shown below:
Voucher Number
|
Item Description
|
Amount
|
08-034
|
LMC
|
$ 433.60
|
08-035
|
GRAY & OSBORNE
|
$ 4,144.24
|
08-036
|
WALTER CAIRNS
|
70.00
|
08-037
|
LEE AMUNDSON
|
808.46
|
08-038
|
SUSAN BARTKUS
|
69.26
|
08-039
|
CASCADE 1
|
139.95
|
08-040
|
VIRGINIA BROWN
|
200.00
|
08-041
|
L&I TAXES
|
5.69
|
Public Forum:
There were no public
comments at this meeting.
Old Business:
- The Montgomery/Condon
Lane Drainage Improvement Project was discussed, with Engineer Barry Baker
reporting that the project has been awarded to Seton Construction. As per
requirements, the pipe has been delivered so the contractor has officially
mobilized and Seton will be on site Monday July 28, 2008; it will take
approximately two (2) weeks to lay the pipe, and an additional two (2) to four
(4) weeks for paving to be done by subcontractors. Mr. Baker addressed
concerns from residents and PLDD Commissioners about the replacement materials
for driveway restoration, stating that the restoration will be as strong or
stronger, than it was prior to construction. Concrete will be replaced with
concrete, asphalt with asphalt; at Jefferson County’s request and cost, gravel
will be replaced with asphalt. Large vegetation (such as bushes) will be dug
up and replaced; smaller plantings will not be replaced but will most likely
grow back in a short time. Measures will be taken to avoid excavating any
more than necessary. Seton Construction was the only company to submit a bid
on April 10, 2008 in the amount of $99,607.95 for completion of this project,
their bid being well under the engineer’s estimate of $130,000.00 and was
divided into three (3) schedules. Schedule A being the Port Ludlow Drainage
District (PLDD) portion of improvements to Montgomery Lane which will connect
to the existing system, at a cost of $32,435.99, with an additional water line
at $1,255.27: Schedule B would be the Jefferson County portion of
improvements to Montgomery Lane at $28,094.57, and Schedule C the Jefferson
County portion of Condon Lane improvements at $16,629.92. In addition, total
fixed costs will be $21,192.20, with approximately one-third of this amount to
be paid by Jefferson County, the remainder by PLDD.
- Engineer Baker reported
that he will finish the Baldwin Lane Feasibility Study next week when
he returns to the area with tools necessary to allow him access to complete
the repair. He will use expandable foam adhering to metal to re-channel water
flow.
- Plans for the McCurdy
Lane Easement project were discussed. Chairman Commissioner Leland
Amundson reported that easement documents were obtained and have been
recorded. The engineering firm of Gray and Osborne, consultants for PLDD,
submitted a letter recommending that Seton Construction be awarded the
contract for this project, theirs being the only bid submitted in the amount
of $31, 056.60, slightly more than the engineer’s estimate of $28,178.16.
Commissioner Amundson felt there were sufficient funds in the budget to take
care of the overage. Commissioners James Laker and Walter Cairns agreed. By
a motion duly made, seconded and unanimously approved, PLDD Commissioners
awarded the McCurdy Lane Drainage Improvement Project Contract to Seton
Construction. Mr. Baker will deliver the contracts to Seton Construction.
Mr. Baker also reported that one other easement has been received, this one at
the downstream end and more critical to completing the project, leaving only
one easement not granted yet; this easement being at the upstream end. The
project will be able to move forward without the easement being submitted, it
just won’t be extended to that area.
- Discussion was held
pertaining to the Status of proposed UDC changes. This will now be
titled the PLDD/ Jefferson County Administrative Rule Agreement, as
Chairman Commissioner Amundson pointed out that there will be no changes made
to the UDC. Significant progress has been made on the draft of a written
agreement between Jefferson County Planning Staff and the PLDD. Barry Baker
reports that there has been a lot of communication between Jefferson County
and himself regarding revisions which will include commercial developments as
well as plats and private residences, with Jefferson County being responsible
for inspections. Mr. Baker anticipates that this draft will be finalized
prior to the next PLDD meeting. Since April, 2008 the PLDD has been working
with the Planning Staff to comprise what would best serve both entities
regarding the Status of proposed UDC changes that were submitted to the county
in April of 2006 by the PLDD, regarding the preference of Jefferson County to
use infiltration, which is not optimal in the Port Ludlow Drainage District.
Direct discharge is the preferred means of drainage here, with dispersion
second and infiltration last. The PLDD had been advised to go through an
administrative change via Jefferson County Planning Staff for these changes
rather than a UDC Amendment, in which case the County would be forced to
charge high fees. PLDD Commissioners agreed that whatever the case, a written
agreement of some form needed to be obtained.
- Engineer Barry Baker
reported that a cost estimates for the Wastewater Treatment Ditch,
are almost three (3) times more than originally anticipated. PLDD
Commissioners and Mr. Baker examined what ramifications postponing and/or
proceeding at this time with this project would have on the budget, and
whether it would be more prudent to budget the project for next year, thereby
being able to combine mobilization costs with 2009 projects. PLDD
Commissioners determined that there was no immediate urgency for completion as
the flooding that had occurred in that area was a nuisance that only affected
the parking lot, water had not posed a threat to homes. Consequently, by a
motion duly made, seconded and unanimously carried, PLDD Commissioners
discontinued Wastewater Treatment Ditch plans along with the funds budgeted
for this project in 2008 and moved said plans and budget to proceed forward to
2009.
- Discussions pertaining
to the Rainier to Oak Bay Greenbelt Drainage project were held.
Commissioner Walter Cairns asked Barry Baker prior to this meeting to comment
on the terms of a Public Works Trust Fund (PWTF) loan and what it would mean
to the assessment, these are low-interest loans to local governments that have
critical public works needs; eligible activities include repair, replacement,
reconstruction and improvement of eligible public works systems to meet
current standards for existing users. As a Special Purpose District, the PLDD
would be eligible for a PWTF loan of up to $1,000,000.00 for the
Pre-Construction loan with an interest rate of ½% with 15% matching funds, for
five (5) years. This could then be rolled into a Construction loan with the
same percentage rates for twenty (20) years. An example given by Mr. Baker was
financing a 20 year loan at ½ % interest, assuming that it would be
$500,000.00; the payments would be $40,121.00 per year for 20 years.
Currently, reports Mr. Baker, capital improvement projects are budgeted at
$100,000.00 per year, if the PWTF loan is chosen; this budget could drop by
about $60,000.00 from what it is currently. Commissioner Cairns expressed
concern about getting an easement from Ludlow Maintenance Commission (LMC) at
the ends of the streets for the Rainier to Oak Bay Greenbelt Drainage
Project. Barry Baker said it would be possible to get an estimate on what
that would cost from a MAI, Master Appraiser who would be able to give a
state recognized estimate and/or consultation.
- There was nothing to
report on for the Assessment Methodology Review as per RCW 85.38.
During the June 2008 PLDD Meeting by a motion duly made seconded and
unanimously approved Commissioners directed Engineer Barry Baker to prepare
for signature a letter to the Jefferson County Council regarding preparation
for Assessment Methodology Review as per RCW 85.38, which is required every
four (4) years, stating that the PLDD has no plans to change current accepted
methodology.
New Business:
·
Commissioner Cairns reported that
there is new construction being done at the intersection of Evans Lane and
Talbot, with many trees being taken down.
The next regularly
scheduled meeting of the Port Ludlow Drainage District will be held on Thursday
August 11, 2008 at 10:00 a.m., at the Beach Club in the Bay View Room.
The July 10, 2008 meeting
adjourned at 10:42 a.m.
Respectfully Submitted:
Approved: Approved:
James Laker
Walter Cairns Lee Amundson
Drainage District Drainage
District Drainage District
Secretary Commissioner
Chairman &Treasurer